Wastewater network and treatment improvement

Project: Kirklevington Transfer

Client: ESH-Stantec

Undertaken by Northumbrian Water, the Winep – Kirklevington Transfer was part of a £5 million scheme to improve the performance and flexibility of the area’s wastewater network and wastewater treatment.
DMJ undertook the installation of 1200m of 225mm MDPE pipe, including the installation of all related air valves and washouts with the construction of all the chambers. Street works involved excavating 200m of the carriageway to a depth of 2.2 and installing pre-welded pipe to avoid egress into the excavation. Gravel was then laid on top of the laid pipe, followed by foam backfill into the trench to within 200mm of the surface to allow the carriageway to be reinstated. With all pipe installed, DMJ pressure tested the whole line to 7 bar. The completed pipeline was left full of water until the client was ready for the final connection.

Careers Request

Fill out the form below, and we will be in touch when we have a suitable role.

Contact Information
Role Information